Stormwater Installation, Preston

In September 2020, we worked with Sustainable Homes Melbourne to install a huge stormwater retention and pump pit system in Preston as part of a home renovation/ extension.

We were restricted with the amount of onsite staff we could have due to the COVID19 industry restrictions in place at the time. This meant we had to coordinate traffic management, deliveries, sub-contractors and staff to ensure we could meet the project deadlines as well as the government restrictions. The installation comprised of four 600 x 600mm custom made concrete pits, 41 meters of 525mm Stormpro drains and a massive 3,000 litre dual pump station, with alarm system.